| Other Hard Costs |  |  |  | 
									
										| Carrying cost for intransit offshored product if paid before shipment | $0.00 | $37.50 | shipment time in years X interest rate X price | 
									
										| Carrying cost for inventory on-site | $22.22 | $35.94 | unit price X ( avg. cycle inventory mos. + safety stock mos. + buffer stock mos.) / 12 X carrying cost % | 
									
										| Prototype cost | $0.00 | $0.01 | prototype cost/annual units/product life | 
									
										| End-of-life inventory | $34.44 | $53.75 | 1/12 x unit price x (Delivery time + avg. inventory) x annual quantity/annual quantity/product life | 
									
										| Travel: start-up | $0.00 | $0.01 | start-up cost / annual units / vendor life | 
									
										| Travel: audit/maintain | $0.18 | $0.14 | annual # of trips X (per trip cost of travel time + expense) / annual units | 
									
										| Pick/place into local inventory | $2.50 | $0.50 | (1- % of inventory delivered JIT) x U.S. unit price x pick and place cost as % of U.S. unit price | 
									
										| Purchasing cost, excluding travel | $60.00 | $80.00 | U.S. unit price x purchase cost % | 
									
										| Total Other Hard Costs | $119.35 | $207.85 |  | 
									
										| Cumulative Total | $2,159.35 | $2,041.91 |  | 
								
								
									| Risk |  |  |  | 
									
										| Emergency air freight | $0.00 | $0.81 | % air freighted x (unit weight + unit pkg. weight) x air freight rate | 
									
										| Rework/quality | $4.00 | $4.50 | unit price X quality cost % | 
									
										| Product liability non-recovery risk | $4.00 | $4.50 | unit price X liability risk cost % | 
									
										| IP risk | $2.00 | $3.00 | unit price X IP risk cost % | 
									
										| Opportunity cost: lost orders, slow response, lost customers | $4.00 | $1.50 | unit price x opportunity risk cost % | 
									
										| Economic stability of the supplier | $2.00 | $4.50 | unit price x supplier economic instabiltiy risk | 
									
										| Political stability of the supplier | $2.00 | $4.50 | unit price x supplier political instabiltiy risk | 
									
										| Total Risk | $18.00 | $23.31 |  | 
									
										| Cumulative Total | $2,177.35 | $2,065.22 |  |